Bond 2022 Cost Estimates
-
Total Estimated Costs of Bond 2022 = $298,265,186
Growth and Reinvestment = $197,000,000
Capital Improvement Plan (all schools / aging facilities) — $40,400,000
Elementary School Projects — $1,100,000
- Woodland Elementary, additional parking lot — $700,000
- Madison Place Elementary, drainage around building and south parking lot — $400,000
Middle School Project — $62,500,000
- Santa Fe Trail Middle School building replacement — $62,500,000
Preventative Maintenance Programs — $31,000,000
- Roofing over five years — $10,000,000
- HVAC over five years — $10,000,000
- Track over five years — $2,500,000
- Asphalt / Concrete over five years — $8,500,000
Furniture Replacement over five years — $10,000,000
Second Transportation Center (former Service Center campus) — $5,000,000
Lindenwood Business Center Purchase — $5,000,000
Lindenwood Business Center Full Renovation — $21,000,000
New Service Center Campus — $21,000,000
Technology and Innovation = $60,704,986
2022 Costs — $19,560,000
- 3,400 Elementary desktops — $2,720,000
- 650 Mac labs — $975,000
- 2,500 High school student Windows tablets — $1,500,000
- 1,100 Support building laptops — $660,000
- Hyperflex DC 1 replacement — $1,500,000
- Routers — $800,000
- 2 Firewalls — $500,000
- WAN rack upgrade (phase 1) — $1,700,000
- 10 Middle school stage sound systems — $600,000
- 15 High school music sound systems — $105,000
- ERP system — $8,500,000
2023 Costs — $9,009,986
- 1,100 Elementary laptops — $660,000
- 650 Mac labs — $975,000
- 2,500 High school student Windows tablets — $1,500,000
- 1,500 Elementary staff Windows tablets — $2,100,000
- 800 High school staff Windows tablets — $1,120,000
- 200 Support building Windows tablets — $280,000
- 500 High school sound systems and AV — $1,000,000
- 100 Support building sound systems and AV — $200,000
- 225 TVs at Olathe West High School — $675,000
- 121 Elementary printers — $121,000
- 104 Middle school printers — $104,000
- 197 High school printers — $197,000
- 18 Support building printers — $18,000
- Elementary copiers — $24,264
- Middle school copiers — $7,414
- High school copiers — $22,242
- Support building copiers — $6,066
2024 Costs — $22,135,000
- 1,600 Middle school desktops — $1,280,000
- 300 High school business / ILL labs — $300,000
- 2,500 High school student Windows tablets — $1,500,000
- 300 AutoCAD labs — $750,000
- 500 Support building desktops — $400,000
- 18,000 Elementary iPad refresh — $9,000,000
- Hyperflex DC2 — $750,000
- 2,700 Access points — $4,050,000
- 4 Controllers and servers — $1,200,000
- 1,400 Elementary sound systems and AV — $2,800,000
- 35 Mill Creek Campus sound systems and AV — $105,000
2025-26 Annual Cost — $10,000,000
Student Experience = $32,315,000
Elementary School Projects — $6,800,000
- 34 Elementary school playground surfacing / equipment — $6,800,000
High School Projects — $9,500,000
- 4 High school turf field replacements — $4,000,000
- 1 High school media center renovation — $5,500,000
Middle School Projects — $4,000,000
- 8 Middle school auditorium renovations — $4,000,000
Career Technical Education — $5,000,000
District Athletic Complexes (CBAC and ODAC) — $7,015,000
- ODAC long jump pit renovations and pit covers — $250,000
- 150 Parking lot light poles changed to LEDs — $250,000
- Field lighting changed to LED — $2,000,000
- 16 Batting cage / bullpen turf replacements — $800,000
- 11 Scoreboard replacements (soccer, baseball, softball) — $440,000
- Reinforce existing bleachers (soccer and visitor side football) — $75,000
- Elevator for ODAC pressbox — $200,000
- New baseball/softball DAC facility (1 field each) — $3,000,000
Safety = $8,245,200
Overall District Safety Projects — $8,245,200
- Olathe South / Indian Trail Middle School traffic circulation: road to Heritage Elementary and modifications — $1,700,000
- Districtwide upgrade to Access Control Manager readers and migration — $3,600,000
- 50 Avigilon server upgrades — $1,250,000
- 6 Vape sensors at Mill Creek Campus — $7,200
- 40 Vape sensors at middle schools — $48,000
- 6 Additional middle school cameras — $60,000
- Additional elementary school playground cameras — $150,000
- Education Center camera system — $50,000
- 2 Additional DAC cameras — $100,000
- Current Operations Service Center camera system — $40,000
- Lone Elm Service Center camera system — $40,000
- Olathe South cellular service BDA upgrade — $100,000
- Additional building / district radios — $100,000
- Additional elementary school interior cameras — $1,000,000